QUANTITY TAKE-OFF AND UNIT PRICE ANALYSIS FOR THE ESTATE SEPAKU HOUSING PROJECT, PENAJAM PASER UTARA REGENCY
DOI:
https://doi.org/10.58641/cest.v5i1.261Keywords:
construction cost estimate, quantity take-off, Unit Price Analysis, housing projectAbstract
Housing development in the buffer area of Indonesia's Nusantara Capital City (IKN) requires accurate, location-sensitive cost estimates, yet the cost structure of such projects remains poorly documented. This study analyzes the Cost Budget Plan (Rencana Anggaran Biaya/RAB) of the Estate Sepaku Housing Project in Penajam Paser Utara Regency using quantity take-off and Unit Price Analysis (Analisis Harga Satuan Pekerjaan/AHSP). A quantitative descriptive case study was applied to a work package of 20 housing units and supporting site infrastructure on a 2,211 m² site with 1,055 m² of building floor area, using working drawings, technical specifications, PUPR Regulation No. 8 of 2023, and the 2023 regional Standard Price List of Goods and Services (SHBJ). Work items were identified, quantities were calculated and reconciled against the cost recapitulation, AHSP-based unit prices were applied, and costs were recapitulated by work group. The total construction cost was Rp4,240,234,957, equivalent to Rp212,011,748 per housing unit and Rp4,019,180 per m² of building floor area, excluding taxes and other non-construction cost components. Wall work dominated at Rp1,202,854,210 (28.37%), followed by roofing work (18.62%), door and window frame work (11.57%), and structural work (11.12%); together these four groups accounted for 69.67% of the total. The novelty of this study lies in mapping the cost drivers of repetitive housing construction in the IKN buffer area, providing normalized cost benchmarks and identifying the work groups that should receive priority in procurement planning and budget control.
References
Abdullahi, A. M., Ibrahim, Y. M., Kolo, B. A., & Abanda, F. H. (2019). An Ontology for Detailed Measurement of Building Works Using Semantic Web Technology. International Journal of Digital Innovation in the Built Environment, 8(1), 42–63. https://doi.org/10.4018/IJDIBE.2019010104
Alwarizi, F., & Sari, S. N. (2024). Analisis Biaya dan Waktu dengan Metode Nilai Hasil pada Proyek Pembangunan Gedung Balai Nikah dan Manasik Haji KUA Kecamatan Rao, Kabupaten Pasaman. STORAGE: Jurnal Ilmiah Teknik Dan Ilmu Komputer, 3(1), 80–88.
Arianie, G. P., & Puspitasari, N. B. (2017). Perencanaan Manajemen Proyek Dalam Meningkatkan Efisiensi dan Efektifitas Sumber Daya Perusahaan (Studi Kasus : Qiscus Pte Ltd). J@ti Undip : Jurnal Teknik Industri, 12(3), 189. https://doi.org/10.14710/jati.12.3.189-196
Bozgulova, N., Parmanova, R., Abenova, M., Ivanyuk, T., & Aryshev, V. (2019). Calculation methods for cost management in the construction industry. Entrepreneurship and Sustainability Issues, 7(2), 1450–1461. https://doi.org/10.9770/jesi.2019.7.2(46)
Delsi, A. M., Lulu, L., Manubulu, C. C., & Usboko, G. P. (2022). Analisis Perbedaan Analisa Harga Satuan Item Pekerjaan Pada Rencana Anggaran Biaya dan Pelaksanaan (Studi Kasus : Proyek Preservasi Jalan Lingkar Luar Kota Kupang). Eternitas: Jurnal Teknik Sipil, 1(2), 41–47. https://doi.org/10.30822/eternitas.v1i2.1596
Fazeli, A., Dashti, M. S., Jalaei, F., & Khanzadi, M. (2021). An integrated BIM-based approach for cost estimation in construction projects. Engineering, Construction and Architectural Management, 28(9), 2828–2854. https://doi.org/10.1108/ECAM-01-2020-0027
Ferdinand, F., & Pamadi, M. (2023). Perbandingan Biaya Pembangunan Rumah: SNI 2008, AHSP 2022 atau Perhitungan Kontraktor? Jurnal Ilmiah Telsinas Elektro, Sipil Dan Teknik Informasi, 6(2), 172–187. https://doi.org/10.38043/telsinas.v6i2.4627
Graham, K., Chow, L., & Fai, S. (2018). Level of detail, information and accuracy in building information modelling of existing and heritage buildings. Journal of Cultural Heritage Management and Sustainable Development, 8(4), 495–507. https://doi.org/10.1108/JCHMSD-09-2018-0067
Harahap, S. (2021). Analisa Perbandingan Biaya serta Waktu Pelaksanaan Material Dinding Batu Bata dan Batako pada Rumah Type 36. Jurnal Education and Development, 9(3), 20–26.
Hu, M., & Skibniewski, M. J. (2021). A Review of Building Construction Cost Research: Current Status, Gaps and Green Buildings. Green Building & Construction Economics, 1–17. https://doi.org/10.37256/gbce.212021768
Nurcahyani, D., & Sari, S. N. (2023). Analisis Perbandingan Biaya Pembangunan Rumah Konvensional 1 Lantai Tipe 40 Menggunakan AHSP 2016 dan AHSP 2022 (Studi Kasus: Rumah di Triharjo, Kabupaten Sleman).
Permadi, A., Waluyo, R., & Kristiana, W. (2018). Analisis Estimasi Biaya Konstruksi Menggunakan Analisis Harga Satuan Pekerjaan 2013 dan 2016. Jurnal Teknika: Jurnal Teoritis Dan Terapan Bidang Keteknikan, 2(1), 1–12.
Rianto, I., Maulana, R., & Sari, S. N. (2026). Analysis of Partial Rehabilitation Costs of Earthquake-Resistant Simple House Structures in Bantul Regency. G-Tech: Jurnal Teknologi Terapan, 10(1), 348–357. https://doi.org/10.70609/g-tech.v10i1.8833
Sa’adah, A. I. U., Sari, S. N., & Maulana, R. (2025). Analysis of Cost Budget Plans in Disaster Logistics Warehouse Planning of the Badan Penanggulangan Bencana Daerah (BPBD) Bantul Regency, D.I. Yogyakarta. G-Tech: Jurnal Teknologi Terapan, 9(1), 229–238. https://doi.org/10.70609/gtech.v9i1.6033
Stringer, S., Jusmidah, J., Fikri, M., & Nurhidayah, N. (2025). Analisis Persepsi Penerapan Manajemen Proyek Terhadap Keberhasilan Suatu Proyek Konstruksi. Jurnal Ilmiah Ecosystem, 25(1), 185–195. https://doi.org/10.35965/eco.v25i1.5869