SCHEDULE DEVIATION EVALUATION OF A THREE-STORY BOARDING HOUSE PROJECT USING EARNED VALUE MANAGEMENT
DOI:
https://doi.org/10.58641/cest.v5i1.262Keywords:
Earned Value Management, project schedule performance, Planned Value, Earned Value, project delayAbstract
Delays in construction projects affect the achievement of completion targets, so a control method that evaluates schedule performance effectively is required. This study evaluates the schedule performance of a three-story boarding house project at Gg. Menur, Ngropoh, Condongcatur, Depok, Sleman using a schedule-based Earned Value Management (EVM) approach. Because the project Bill of Quantities (BoQ) was not available, Planned Value (PV) and Earned Value (EV) are represented by cumulative percentages of physical progress rather than by budgeted cost values. The approach is therefore a modified, schedule-only application of EVM: it measures schedule performance alone, and cost indicators such as Cost Variance (CV) and Cost Performance Index (CPI) are outside its scope. A quantitative descriptive approach was applied to the project time schedule and weekly progress reports, and performance was analyzed through Schedule Variance (SV) and Schedule Performance Index (SPI), with weeks classified using a predetermined tolerance band of SPI = 1.00 ± 0.05. At the end of week 35 the PV reached 100% while the EV reached only 76.224%, giving an SV of −23.776 percentage points and an SPI of 0.76. Of the 35 weeks, 60% were ahead of schedule, 14.29% within tolerance, and 25.71% delayed, with sustained delay from week 27. The actual progress rate remained almost constant at about 2.2 percentage points per week throughout, whereas the plan required it to double after week 25, indicating that the deviation arose from a back-loaded baseline rather than from a decline in site productivity. An Earned Schedule analysis gives an estimated duration of approximately 42.6 weeks, about 7.6 weeks beyond the plan.
References
Adhitya Putra, D., Lhara Sari, O., & Situmorang, R. (2023). Factor analysis of construction projects delay in Balikpapan City. Jurnal Teknik Sipil: Rancang Bangun, 9(1), 17–24.
Aldammak, M. M., Hamzah, N., & Khoiry, M. A. (2025). Causes for the delay in construction offices building: A systematic review. Jurnal Kejuruteraan, 37(5), 2453–2467. https://doi.org/10.17576/jkukm-2025-37(5)-33
Anbari, F. T. (2003). Earned value project management method and extensions. Project Management Journal, 34(4), 12–23. https://doi.org/10.1177/875697280303400403
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010
Auliasari, V. R., Setyaning, L. B., & Nusantoro, A. (2023). Analisis pengendalian waktu dan biaya proyek konstruksi dengan metode earned value. Jurnal Teknik Sipil, 7(1), 185–193.
Citeladze, D. (2023). Project management (pp. 1–24). https://doi.org/10.12737/1859087
Creswell, J. W. (2014). Research design: Qualitative, quantitative, and mixed methods approaches (4th ed.). SAGE Publications.
Ervianto, W. I. (2007). Manajemen proyek konstruksi (Revised ed.). Andi.
Johari, G. J., & Islami, N. N. (2022). Analisis biaya dan waktu menggunakan metode earned value concept pada proyek MBE well hook up. Jurnal Konstruksi, 19(1), 325–335. https://doi.org/10.33364/konstruksi/v.19-1.973
Junaidi, J., Supriyadi, S., Candradewi, A., & Pradikdya, A. B. (2022). Kajian evaluasi biaya dan waktu dalam penanganan keterlambatan proyek menggunakan metode earned value analysis (Studi kasus: Proyek Pembangunan Jalan Layang Akses Bandara Jenderal Ahmad Yani Semarang). BangunRekaprima, 8(1), 51–60. https://doi.org/10.32497/bangunrekaprima.v8i1.3528
Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). John Wiley & Sons.
Khamooshi, H., & Golafshani, H. (2014). EDM: Earned Duration Management, a new approach to schedule performance management and measurement. International Journal of Project Management, 32(6), 1019–1041. https://doi.org/10.1016/j.ijproman.2013.11.002
Lipke, W. (2003). Schedule is different. The Measurable News, 31(4), 31–34.
Lipke, W., Zwikael, O., Henderson, K., & Anbari, F. (2009). Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes. International Journal of Project Management, 27(4), 400–407. https://doi.org/10.1016/j.ijproman.2008.02.009
Mekonen, E. K., Shedaga, T., & Sahle, M. (2025). Determinants of construction project delay and its effect on project beneficiaries: Evidence from the Gurage Zone, Ethiopia. Discover Civil Engineering, 2(1). https://doi.org/10.1007/s44290-025-00163-6
Mokoagow, F. N., Maulana, R., Ardian, O. H., & Sari, S. N. (2024). Analisa penerapan manajemen waktu pada proyek pembangunan gedung unit pelayanan teknis pusat balai latihan kerja Bantul. STORAGE: Jurnal Ilmiah Teknik dan Ilmu Komputer, 3(1), 88–97.
Project Management Institute. (2017). A guide to the project management body of knowledge (PMBOK guide) (6th ed.). Project Management Institute.
Septiyanto, I. Y. (2018). Evaluasi kinerja waktu dan biaya pada proyek konstruksi gedung asrama sekolah dengan pendekatan EVA dan percepatan proyek dengan PDM [Undergraduate thesis, Universitas Islam Indonesia].
Sogar, A. U. S., Maulana, R., & Sari, S. N. (2024). Studi tentang keterlambatan pembayaran dari pemilik proyek konstruksi kepada kontraktor. STORAGE: Jurnal Ilmiah Teknik dan Ilmu Komputer, 3(1), 45–54.
Sudjatmiko, L. A. M., Sari, S. N., & Ardian, O. H. (2026). Perbandingan metode Critical Path Method (CPM) dan Precedence Diagram Method (PDM) pada pembangunan rumah tipe 36. JUSTER: Jurnal Sains dan Terapan, 5(1), 11–21.
Sugiyono. (2014). Metode penelitian kuantitatif, kualitatif, dan R&D. Alfabeta.
Vandevoorde, S., & Vanhoucke, M. (2006). A comparison of different project duration forecasting methods using earned value metrics. International Journal of Project Management, 24(4), 289–302. https://doi.org/10.1016/j.ijproman.2005.10.004
Warsika, P. D. (2013). Penjadwalan dan biaya proyek konstruksi menggunakan WBS, CPM, dan PERT. Jurnal Ilmiah Teknik Sipil, 17(1).
Yap, J. B. H., Goay, P. L., Woon, Y. B., & Skitmore, M. (2021). Revisiting critical delay factors for construction: Analysing projects in Malaysia. Alexandria Engineering Journal, 60(1), 1717–1729. https://doi.org/10.1016/j.aej.2020.11.021
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Clean Energy and Smart Technology

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.