COST AND ON-SITE DURATION COMPARISON OF CONVENTIONAL AND PRECAST FLOOR SLAB METHODS: A TWO-STORY BOARDING HOUSE CASE STUDY IN YOGYAKARTA
DOI:
https://doi.org/10.58641/cest.v5i1.268Keywords:
Conventional Floor Slab, Precast Floor Slab, Construction Cost, On-Site Duration, Case StudyAbstract
Floor slab construction strongly affects both the cost and the on-site duration of low-rise buildings, yet transparent project-level comparisons for small boarding houses remain scarce. This study compares the direct cost and on-site construction duration of conventional cast-in-place and precast floor slab methods for the 50.36 m² second-floor slab of a two-story type-135 boarding house in Pugeran, Yogyakarta. A quantitative comparative case study was applied using project drawings, an itemized quantity take-off, the Indonesian Unit Price Analysis (AHSP), documented local price bases, a supplier quotation, and labor-based duration calculations. The conventional alternative cost IDR 35,746,962.53 and the supplier-inclusive precast alternative IDR 30,216,000.00, a project-specific saving of IDR 5,530,962.53 (15.47%), while the calculated on-site duration fell from 11 days to 2 days, a reduction of 9 days (81.82%). A sensitivity analysis shows that the cost advantage reverses once the precast price rises by about 18%, identifying the condition under which the conventional method becomes cheaper. The reported savings apply only to the prices, crew composition, and work scope adopted in this case study; they exclude factory lead time and curing, and they do not constitute structural verification of the precast system.
References
Ahmad, O., Sadeghi, K., & Nouban, F. (2023). Comparison of the post-tensioned, solid, hollow block, and flat slabs in terms of economy considering different span lengths. International Journal of Applied Mechanics and Engineering, 28(2), 24–33. https://doi.org/10.59441/ijame/168936
Antoni, A., & Nugraha, P. (2007). Teknologi beton. Yogyakarta: C.V. Andi Offset.
Badan Pusat Statistik Daerah Istimewa Yogyakarta [BPS DIY]. (2021). Statistik penduduk Yogyakarta 2021. BPS DIY.
DEPOHEBELYOGYA. (2026). Harga panel lantai di Sleman 2026: Informasi harga dan spesifikasi panel lantai pracetak [Supplier price quotation]. Retrieved February 2026.
Kementerian Pekerjaan Umum dan Perumahan Rakyat. (2016). Analisis harga satuan pekerjaan (AHSP) konstruksi. Jakarta: Kementerian PUPR.
Nauly, A., Rambe, M. R., & Patriotika, F. (2022). Analisa perbandingan biaya dan waktu pelaksanaan pelat lantai konvensional dengan pelat lantai pracetak pada gedung berlantai tiga. Statika, 5(2), 55–62.
Pemerintah Kabupaten Sleman. (2025). Standar harga barang dan jasa Kabupaten Sleman tahun anggaran 2025. Sleman: Pemerintah Kabupaten Sleman.
Prasetyo, A. (2018). Perbandingan biaya pekerjaan pelat lantai beton bertulang antara metode cor di tempat dan metode pracetak pada bangunan rumah tinggal dua lantai [Undergraduate thesis, Universitas Diponegoro].
Putra, B. (2020). Analisis anggaran biaya pelat lantai beton bertulang pada bangunan rumah kos dua lantai di Yogyakarta [Undergraduate thesis, Universitas Gadjah Mada].
Rahmawati, S. (2022). Studi komparasi biaya pekerjaan struktur lantai menggunakan panel lantai beton ringan pada bangunan sederhana dua lantai [Undergraduate thesis, Universitas Sebelas Maret].
Riyadi, I., Handayani, E., & Dony, W. (2022). Analisa perbandingan sistem pelat konvensional dengan sistem precast half slab dalam segi waktu dan biaya. Jurnal Civronlit Unbari, 7(2), 63–69. https://doi.org/10.33087/civronlit.v7i2.100
Romadhoni, M., & Sahid, M. N. (2023). Efektivitas metode pekerjaan pelat lantai bondek, half precast dan konvensional gedung asrama putra Al-Azhar. Jurnal Manajemen Teknologi & Teknik Sipil, 6(2), 99–111. https://doi.org/10.30737/jurmateks.v6i2.4949
Santoso, D. (2021). Perbandingan biaya dan waktu pelaksanaan antara sistem pelat lantai konvensional dan sistem pracetak pada bangunan hunian bertingkat rendah [Undergraduate thesis, Institut Teknologi Bandung].
Sarhan, O., Raslan, M., & Tallawi, G. (2021). Hollow-core precast and two-way solid slabs: Cost estimation and time duration comparison. International Journal of Advanced Engineering, Sciences and Applications, 2(1), 29–35. https://doi.org/10.47346/ijaesa.v2i1.22
Setiawan, A. (2016). Perancangan struktur beton bertulang berdasarkan SNI 2847:2013. Jakarta: Erlangga.
Soeharto, I. (1999). Manajemen proyek: Dari konseptual sampai operasional. Jakarta: Erlangga.
Tedja, M., Prisilla, A., Carolina, Wiharyanto, D. E. J., & Susiyo, J. (2013). Perbandingan metode konstruksi plat lantai sistem double wire mesh dengan sistem half slab. ComTech, 4(2), 888–895. https://doi.org/10.21512/comtech.v4i2.2527
Trijeti, Atmawan, F. D., & Aswanto, M. (2018). Time and cost comparison of conventional and alternative plate hollow slab, half slab, and metaldeck. International Journal of Scientific & Technology Research, 7(6), 61–66.
Wibowo, A. (2019). Penggunaan panel lantai beton ringan pada bangunan bertingkat rendah. Jurnal Teknik Sipil, 15(2), 101–112.
Wijaksono, O., Tistogondo, J., & Bagio, T. H. (2018). Analisis perbandingan efisiensi waktu dan biaya antara metode konvensional slab, precast half slab dan precast full slab pada proyek bangunan hotel bertingkat di Surabaya. Prosiding Seminar Nasional Sains dan Teknologi (Semnastek), 1–9.
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Clean Energy and Smart Technology

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.